Warehouse Lighting Audit Checklist: High Bays, Racking and Controls

Writer: LumaQuote
LumaQuote
1 day ago
5 min read

Updated: 7 hours ago

A warehouse lighting audit starts with the work areas, racking and fixture locations. Record the light levels, operating hours, controls and access for each area before pricing the retrofit.



Warehouse lighting audit checklist


Survey section

Record on site

Why it changes the estimate

Areas and tasks

Storage, picking, packing, docks and support spaces

Different tasks need different lighting decisions

Geometry

Mounting heights, rack heights, aisle widths and obstructions

Affects distribution, layout and access

Existing equipment

Fixture type, lamp count, input watts and condition

Establishes the baseline and installation scope

Light measurements

Location, plane, units, controls state and daylight

Makes the observations interpretable

Operating schedule

Hours by area, shifts and shutdown periods

Drives energy estimates

Controls

Existing zones, sensors, timeouts and dimming

Defines the baseline and proposed control scope

Installation access

Lift routes, floor restrictions and work windows

Changes equipment, labor and staging costs

Evidence

Area IDs, fixture IDs, photos and open questions

Supports the estimator's handoff


For other building types, use the general lighting audit checklist.


1. Separate the work areas


Give separate IDs to storage, rack aisles, picking, packing, receiving, docks and offices. Split them further where the fixtures, hours or controls differ.


Note where people work and what they need to see, including labels on rack faces. Mark mezzanines, conveyors, cranes and other equipment that blocks light or access.


Warehouse aisle between tall red storage racks, with industrial lighting above.
Map fixture groups to aisle numbers.

Mark the plan and photo filenames with the same area IDs.


2. Record mounting heights, racking and obstructions


Record fixture mounting height and work-plane height, plus rack heights, aisle widths, rack orientation and cross-aisles.


Photograph the warehouse under normal storage conditions. Ask about planned rack moves, changes in stock height or future fit-outs.


Use the high-bay calculator for an initial quantity and spacing check. Get a photometric design when the site conditions or project specification require one.


3. Inventory the existing fixtures and input power


For each consistent fixture group, record:


  • Area ID, group ID, quantity and location reference.

  • Fixture type and any readable manufacturer or model label.

  • Lamp type, lamp count and ballast or driver information.

  • Input watts, source of the value and confidence in that value.

  • Mounting arrangement, condition and failed or disconnected units.

  • Controls assignment and any emergency or special-purpose function.

  • Photographs of the fixture, label and relevant surroundings.


Use whole-fixture input watts, including the ballast or driver. Mark estimated values and note what to check before finalizing savings.


The LED wattage chart gives starting values for common fixture types. Verify them against the equipment on site.


4. Measure light at the task


Log the meter, date, units, point location, measurement plane, sensor height and orientation. Note daylight, controls state and failed fixtures.


Measure rack faces where workers read vertical labels, as well as the relevant horizontal work surfaces. Keep the individual readings, minimum and average.


How many foot-candles does a warehouse need?


Set light-level criteria for each task: storage, picking, packing, inspection and circulation. Use those criteria when reviewing the proposed layout.


For warehouse design guidance, use the IES industrial-lighting resources and RP-7 recommended practice.


OSHA’s 1926.56 table covers construction illumination. Check which workplace, energy-code and emergency-lighting requirements apply to this project.


5. Confirm operating hours by area


Confirm actual lighting-on hours with the site operator. Include shifts, weekends, holidays, shutdowns and any overnight use.


Different zones can have different hours. Receiving may start earlier than picking; a security or circulation zone may remain on after storage aisles dim.


For example, 16 lighting-on hours a day × 5 days a week × 50 weeks a year gives 4,000 hours. Account for existing sensors and dimming when calculating baseline consumption.


6. Audit the controls already installed


Map which fixtures belong to each switch, sensor, schedule or dimming zone. Record timeouts, daylight response, overrides and the observed occupied and unoccupied states.


Ask operators about sensors that switch off too soon, blocked coverage, overrides and faults. Establish how the current controls operate before estimating savings from new controls.


Include controls hardware and commissioning in the quote. Use the controls checklist and DOE selection guidance to define that work.


7. Survey installation access and work windows


Check lift routes, aisle clearance, turning space, floor restrictions and work-zone isolation. Agree on who moves stock and where crews will stage materials.


Agree on work windows, security, deliveries and waste collection. Check whether conveyors or racking prevent access under the fixtures.


Allow for rental days, staging and return visits. See the fixture labor allowances and project-cost breakdown when building the estimate.


8. Close the gaps before quoting


Assign an owner to each open question. Label the source of each wattage, schedule and dimension.


Example survey finding

Estimating consequence

High bays above a conveyor

Verify the access method and installation window

Rack-face visibility is poor

Obtain a design addressing the task and distribution

Existing aisle sensors are active

Include their effect in the baseline

Input watts are unknown

Verify power before finalizing savings

Failed fixtures are counted as operating

Resolve baseline treatment before claiming reductions

Loading-dock hours differ from storage

Calculate the areas separately


Confirm the product schedule, lighting criteria, controls, access costs and incentives before sending the quote. Check proposed products with the DLC qualification guide.


Example: calculate savings for one area


For a simple example, take 40 fixtures at 250 watts each running 4,000 hours a year. Replacing them with 40 fixtures at 100 watts gives the following energy calculation.


Calculation

Result

Existing connected load: 40 × 250 ÷ 1,000

10 kW

Proposed connected load: 40 × 100 ÷ 1,000

4 kW

Annual electricity reduction: (10 − 4) × 4,000

24,000 kWh

Annual energy-cost reduction at US$0.15/kWh

US$3,600


Check that the selected fixtures meet the lighting criteria. This example covers energy cost only; installation, controls, maintenance, demand charges, incentives and tax must be assessed separately.


Build the proposal from the survey


LumaQuote warehouse audit inventory with fixture quantities, watts, operating hours and energy estimates.
LumaQuote fixture inventory, grouped by area.

In LumaQuote, enter the area and fixture groups from your survey, then add replacements, operating hours and installation costs.


See a sample proposal and the retrofit workflow. For field-app setup, use the Android or iPad and iPhone guide.


Frequently asked questions


What should a warehouse lighting audit include?


Record areas and tasks, rack and mounting geometry, fixture quantities and input watts, light measurements, operating schedules, controls, installation access, photographs and unresolved questions.


Can a fixture count determine how many LED high bays to install?


Use the existing count as the starting inventory. Confirm the proposed quantity with the required light levels, layout, optics and obstructions before assuming a one-for-one swap.


Should I measure light on the floor or on rack faces?


Measure the planes where the work happens. That can include horizontal work surfaces and vertical rack faces. Record the location, height and orientation for each reading.


How do I estimate warehouse operating hours?


Confirm lighting-on hours by zone with the site operator, including shifts, shutdowns and current controls.


Does the checklist replace a photometric design or compliance review?


No. The checklist supplies survey data. A lighting design and any required electrical or compliance review are separate steps.